S. Belt Line Road

Fiber Installation from Lakeview Dr. to South Belt Line Rd. 

Affected Direction: Northbound

Expected to End: June, 2019


Camp Wisdom Widening

widen Camp Wisdom to four lanes between Carrier and east city limits to extend to FM 1382.

Affected Direction: Eastbound and Westbound  

Expected to End: May, 2019


City Hall Extension

NW 3rd Street and W Church St. closed for central civic campus additions and renovations project.

Affected Direction: Road Closures  

Expected to End: End of 2019


Coral Way

Repair sidewalk and handicap ramp along Coral Way to Cober Dr.

Affected Direction: Westbound and Eastbound

Expected to End: April, 2019


Egyptian Way

Street paving SH 161 on Egyptian Way to Carrier Parkway.

Affected Direction: Eastbound and Westbound  

Expected to End: April, 2019


Great Southwest Parkway

Widening Great Southwest Parkway from four lanes to six lanes from Sara Jane to Mayfield.

Affected Direction: Northbound & Southbound  

Expected to End: In 2020


I-20 Frontage Roads between SH 161 and Belt Line Road

The I-20 frontage roads between SH 161 and Belt Line Road are under construction, with completion set for early 2023, opening 318 acres for new development.

Affected Direction: Northbound & Southbound

Expected to End: In 2023


I-20 Fiber Installation

I-20 Fiber installation from Grand Prairie Premium Outlets to the Parkways at Prairie Creek Apartments.

Affected Direction: Eastbound and Westbound

Expected to End: May, 2019


Lake Ridge Parkway

Replacing concrete panels on Lynn Creek / Mildred Walker Parkway to England Parkway.

Affected Direction:Southbound Lanes Only

Expected to End: End of September 2019


Matthew Road

Corral Drive to South end requires street closure with detours.

Affected Direction: Northbound  

Expected to End: Early October, 2019


Mountain Creek Lake Toll Bridge

The project includes pavement rehabilitation, removal of the existing toll plaza and operations building, construction of new toll gantries, and removal and installation of new pavement markings and signage.

Affected Direction: Westbound

Expected to End: End of 2019


NW 7th

Egyptian to Austrian street potholing for gas lines. Requires closing shoulders.

Affected Direction: Eastbound and Westbound  

Expected to End: June, 2019


Palace Parkway

Extend Palace Parkway from Palace/Belt Line to I-30 looping around vacant properties on northeast corner of IH-30 and Belt Line and connect to new westbound IH-30 frontage road.

Affected Direction: Westbound  

Expected to End: In 2019


Seeton Road

Install underground sanitary sewer line and storm sewer line across Spring Creek Circle.

Affected Direction: Northbound & Southbound

Expected to End: June, 2019


SW 3rd Street

Roadway reconstruction on Marshall Drive to Phillips Court.

Affected Direction: All Lanes

Expected to End: Mid October 2019


Stadium Drive

Asphalt mill and overlay, work limits from Hill Street to Crescent Drive.

Affected Direction: All Lanes

Expected to End: August 2019


SH 360 from I-20 to I-30

TxDOT is adding one southbound and one northbound lane on SH 360 from I-20 to I-30.

Affected Direction: Northbound & Southbound  

Expected to End: In 2020


  • Construction

    Camp Wisdom Road Widening Update

    Camp Wisdom Road project from Carrier Pkwy to Beltline (FM 1382) will widen the existing 2-lane to a 4-lane concrete road.

    10/21/2019 12:13 PM