360 South Project: Construction Underway at New York Avenue

Post Date:06/27/2016 9:48 AM

To allow for construction of the new crossover bridge for the new mainlanes of SH 360 over New York Avenue, the southbound SH 360 to northbound SH 360 turnaround will close. Motorists wishing to go from southbound to northbound SH 360 will use New York Avenue to complete the turnaround.

New York Avenue will remain open at SH 360 during the bridge's construction. Construction of the new bridge is expected to take six to nine months to complete. Once construction of the new mainlane bridge is complete, the turnaround will be reopened.


 

Project Updates

For the most up-to-date information about the project, construction updates and lane closures, visit the project website at drive360south.com, register for e-mail alerts, or follow the project on Facebook and Twitter.

About the SH 360 South Project 

The SH 360 South Project is a $330 million design-build construction project in partnership with the Texas Department of Transportation (TxDOT), North Texas Tollway Authority (NTTA) and the North Central Texas Council of Governments and local cities and counties to improve mobility, enhance safety and connect communities. Once complete, the toll road will be operated by NTTA.

Beginning in fall 2015, the 9.7-mile project will stretch from Green Oaks Boulevard to US 287. The project will provide through lanes that will improve mobility throughout the rapidly developing corridor in addition to improving traffic flow for local businesses and residents along the SH 360 frontage roads. Construction is anticipated to be complete in late 2017. Construction management for the design-build project is led by the Lane | Abrams Joint Venture.

360 South Project Website: www.drive360south.com